Bioprofile of Projects

 

Total Mining Projects sanctioned till date in MCL are 51 (including 3 exhausted Projects). The Rated Production Capacity of these sanctioned Projects is 224.41Mty, with a sanctioned Capital outlay of Rs.12738.75Crs (Including RCE). Out of total 51 Projects, 35 Projects are completed Projects and 16 Projects are On-going Projects. These 16 On-going projects have a capacity of 129.83 MTY with a capital investment of Rs.9184.91Crs.


Project
Category

(Rs. Cr.)

No. of
Projects

Sanctioned

Sanctioned Capacity

(Mty)

Sanctioned
Capital

(Rs. Cr.)
Status
Exhausted
Completed
On-going
100 & above
20
162.50
11618.88
1
17
12
50 to 100
12
26.33
776.67
0
05
04
20 to 50
10
25.00
246.67
1
05
00
Below 20
9
10.58
96.52
1
05
00
Total
51
224.41
12738.75
3
32
16

 

Completed Projects: - 35 Nos. & On-going Projects : - 16 Nos.

 

Sl No. Name of the Project Total PR Cap (MTY) Total Sanctioned Capital(Rs. Cr.) Date of PR Approval
1. Completed Projects till date- 35 Nos. (including 3 exhausted projects) 94.58 3553.84 Completed
2. On-Going Projects:-Total-16 Nos.
A.) TALCHER COALFIELD
1 Ananta OCP Expn. Ph-III 3.00 251.95 31.08.2008
2 Balaram OCP Extension. 8.00 * 209.56 22.12.2007
3 Bharatpur OCP Expn., Ph-II  6.00 95.87 25.06.2003
4 Bharatpur OCP Expn. Ph.-III 9.00 131.39 12.02.2007
5 Bhubaneswari OCP 20.00 490.10 22.12.2007
6 Hingula-II OCPExpn. Ph-III 7.00 479.53 08.11.2008
7 Jagannath Re-organisation  6.00 * 337.66 26.05.2014
8 Jagannath U/G  0.67 80.75 15.10.2001
9 Kaniha OCP 10.00 457.77 22.12.2007
10 Natraj U/G 0.64 92.11 30.01.2001
11 Talcher (W) U/G   0.52 85.08 18.02.2002
  Sub total 64.83 2711.77  
B.) IB VALLEY COALFIELD
12 Basundhara (W) Extn 7.00 * 620.42 07.05.2014
13 Kulda OCP 10.00 372.81 12.01.2005
15 Kulda Expn OCP 5.00 348.16 25.06.2014
16 Siarmal OCP 40.00 3756.36 29.05.2014
17 Garjanbahal OCP 10.00 1375.38 08.11.2014
Sub total 65.00 6473.14  
TOTAL (Ongoing projects) 129.83 9184.91  

GRAND TOTAL (Including capacity of exhausted mines)

224.41 12738.75  

* These are the extensions of original projects annexing additional areas. Hence, there will be no addition in Capacity.

 

Future Projects: - 07 Nos.

Sl No. Name of the Projects PR Cap (MTY) Remarks

1.

Integrated Lakhanpur- Belpahar - Lilari OCP

30.0
(Addl-6.20Mty)

PR approved by MCL Board on 03.02.15. In-principal approval by CIL Board on 12.08.15 for expenditure of Rs.535.80Crs for first year only. Revised PR of 30 Mty including Washery (10 Mty) recommended by MCL Board on 23.12.17 in out sourcing variant. Revised PR submitted to CIL in Mar-18 for approval.

2.

Bharatpur Re-organisation (Expn)

20.0

Approved by 194th MCL Board on 08.09.17. Put up to PAC on 27.10.17. Revised PR as per recommendation of PAC is under preparation at CMPDI.

3.

Balaram Expn. OCP

15.0
(Addl–7.0Mty)

‘In principle’ approval of PR by MCL Board on 31.03.12. Now, Updated Cost Estimate (UCE) is under preparation at CMPDI Ranchi.

4.

Gopalji- Kaniha Expn. OCP

30.0
(Addl-20Mty)

PR of Gopalji-Kaniha Expn OC Project was approved by MCL Board on 20.05.15 and by ESC on 23.09.15 for first year expenditure of Rs.80.15Crs. UCE of Gopalji-Kaniha Expansion (30 MTY) is under preparation.

5.

Kulda - Garjanbahal Expn OCP

40.0
(Addl-15Mty)

Review meeting by Secretary (Coal), MoC on 14.08.2017 – to prepare one Project Report. Work Order issued on 23.08.2017.

6.

Lajkura – Orient Expn OCP

15.0
(Addl-11.31Mty)

After incorporating the changes, the final report was submitted on 31.03.2017. The UCE is to be prepared as per Annual Action Plan-2018-19.

7.

Samaleswari OCP

20.00
(Addl–8.0Mty)

Approved by MCL Board on 21.09.15. Put before 89th Empowered Sub Committee meeting on 10.02.16. Under Preparation at CMPDI, Ranchi.

  Total Additional Capacity – 67.51 Mty